Ngoc Hoi Intersection Project

(Project Sample)

👤 ADMIN
📅 NOVEMBER 14, 2025
📁 UNCATEGORIZED
Ngoc Hoi Intersection Project

PROJECT OVERVIEW

  • 📍 Location: Nha Trang Ward - Khanh Hoa Province
  • 🏗️ Type, Grade: Grade II Transportation Works
  • 💰 Total Investment: 1,350 billion VND
  • 🏢 Investor: Phuc Son Group Joint Stock Company
  • 📋 Contract: No. 22/2016/HDKT-T27

PROJECT DETAILS

Solving Traffic Congestion

Eliminating the intersection between the North-South railway and 23/10 Street, an area frequently congested during peak hours.

Regional Traffic Connection

Creating a new North-South traffic route bypassing the city center, connecting the western area of Nha Trang City with 23/10 Street.

Socio-Economic Development

Creating momentum for socio-economic development for Nha Trang City and surrounding areas, serving as an important connection point with Ring Road 2.

Improving Traffic Safety

Effectively channeling traffic, reducing accidents at the railway intersection area.

Modern Design

The intersection is designed according to a modern multi-level traffic model, combining overpasses and underpasses, ensuring smooth traffic 24/7.

Advanced Construction Technology

Applying 3D BIM technology in design and construction management, ensuring high precision and optimizing progress.

Environmentally Friendly

Integrating modern drainage systems, green landscapes, and energy-saving lighting.

Multi-directional Connection

Directly connecting to 4 main traffic directions, creating favorable conditions for movement within and outside the city.

Preparation Phase (2016-2017)

  • Completed topographical and geological surveys
  • Feasibility study report prepared and approved
  • Technical design and construction drawings

Construction Phase (2018-2020)

  • Construction started: Q1/2018
  • Completed foundation and main structure: Q4/2019
  • Project completion: Q2/2020

Acceptance and Operation (2020)

  • Project acceptance: 06/2020
  • Put into operation: 08/2020
  • Achieved national technical standards

Results Achieved

  • Reduced travel time through the area by 70%
  • Significantly improved traffic safety
  • Won the High Quality Construction Award 2020

Design Team

  • Total: 25 experts
  • Chief Engineers: 3 people (15+ years of experience)
  • Design Engineers: 12 people
  • BIM Specialists: 4 people
  • Survey Specialists: 6 people

Supervision Team

  • Total: 15 experts
  • Chief Supervisor: 1 person
  • Specialized Supervisors: 8 people
  • Field Supervisors: 6 people

Professional Consultants

  • 3 international experts on intersection design
  • 2 professors consulting on structure
  • 5 experts on urban traffic

Phase 1: Survey and Research (6 months)

  • Month 1-2: Topographical, geological, and hydrological surveys
  • Month 3-4: Traffic investigation and demand analysis
  • Month 5-6: Option research and feasibility report

Phase 2: Technical Design (8 months)

  • Month 7-9: Preliminary design of options
  • Month 10-12: Detailed technical design
  • Month 1-2 (next year): 3D BIM modeling

Phase 3: Construction Drawing Design (4 months)

  • Month 3-4: Detailed construction drawing design
  • Month 5: Cost estimation and bill of quantities
  • Month 6: Verification and dossier completion

Total Design Time: 18 months

From January 2016 to June 2017